一,風(fēng)管安裝規(guī)范標(biāo)準(zhǔn)
1、 Code and standard for air duct installation
1.風(fēng)管內(nèi)嚴(yán)禁其他管線(xiàn)穿越;
1. It is forbidden to cross other pipelines in the air duct;
2.輸送含有易燃、易爆氣體或安裝在易燃、易爆環(huán)境的風(fēng)管系統(tǒng)應(yīng)有良好的接地,通過(guò)生活區(qū)或其他輔助生產(chǎn)房間時(shí)必須嚴(yán)密,并不得設(shè)置接口
2. The air duct system for conveying inflammable and explosive gas or installed in inflammable and explosive environment shall be well grounded. It must be tight when passing through the living area or other auxiliary production rooms, and no interface shall be set
3.輸送空氣溫度高于80℃的風(fēng)管,應(yīng)按設(shè)計(jì)規(guī)定采取防護(hù)措施。
3. Protective measures shall be taken for air pipes with air temperature higher than 80 ℃ according to design regulations.
4.室外立管的固定拉索嚴(yán)禁拉在避雷針或避雷網(wǎng)上
4. The fixed cable of outdoor riser shall not be pulled on the lightning rod or lightning protection net
二,風(fēng)管部件安裝必須符合下列規(guī)定:
2、 The installation of air duct components must meet the following requirements:
1.各類(lèi)風(fēng)管部件及操作機(jī)構(gòu)的安裝,應(yīng)能保證其正常的使用功能,并便于操作;
1. The installation of various air duct components and operating mechanisms shall ensure their normal use function and be easy to operate;
2.斜插板風(fēng)閥的安裝,閥板必須為向上拉啟;水平安裝時(shí),閥板還應(yīng)為順氣流方向插入;
2. For the installation of inclined plug plate air valve, the valve plate must be pulled upward; for horizontal installation, the valve plate shall also be inserted along the air flow direction;
3.止回風(fēng)閥、自動(dòng)排氣活門(mén)的安裝方向應(yīng)正確。
3. The installation direction of check air valve and automatic exhaust valve shall be correct.
4.防火閥、排煙閥(口)的安裝方向、位置應(yīng)正確。防火分區(qū)隔墻兩側(cè)的防火閥,距墻表面不應(yīng)大于200mm。
4. The installation direction and position of fire damper and smoke exhaust valve (port) shall be correct. The distance between the fire damper on both sides of the partition wall of the fire compartment and the wall surface shall not be more than 200mm.
5.手動(dòng)密閉閥安裝,閥門(mén)上標(biāo)志的箭頭方向必須與受沖擊波方向一致。
5. For the installation of manual airtight valve, the arrow direction marked on the valve must be consistent with the direction of shock wave.
6.風(fēng)管系統(tǒng)安裝完畢后,應(yīng)按系統(tǒng)類(lèi)別進(jìn)行嚴(yán)密性檢驗(yàn),漏風(fēng)量應(yīng)符合設(shè)計(jì)與風(fēng)管必須通過(guò)工藝性的檢測(cè)或驗(yàn)證,其強(qiáng)度和嚴(yán)密性要求應(yīng)符合設(shè)計(jì)或下列規(guī)定:
6. After the installation of the air duct system, the tightness inspection shall be carried out according to the system category. The air leakage shall meet the design and the air duct must pass the technical inspection or verification, and the strength and tightness requirements shall meet the design or the following requirements:
① 風(fēng)管的強(qiáng)度應(yīng)能滿(mǎn)足在1.5倍工作壓力下接縫處無(wú)開(kāi)裂;
?、?The strength of air duct shall be able to meet the requirement that there is no crack at the joint under 1.5 times of working pressure;
?、?矩形風(fēng)管的允許漏風(fēng)量應(yīng)符合以下規(guī)定:
② The allowable air leakage of rectangular air duct shall meet the following requirements:
低壓系統(tǒng)風(fēng)管 QL≤0.1056P0.65
Low pressure system air duct QL ≤ 0.1056p0.65
中壓系統(tǒng)風(fēng)管 QM≤0.0352P0.65
Medium pressure system air duct QM ≤ 0.0352p0.65
高壓系統(tǒng)風(fēng)管 QH≤0.0117 P0.65
High pressure system air duct QH ≤ 0.0117 p0.65
式中 QL、QM、QH——系統(tǒng)風(fēng)管在相應(yīng)工作壓力下,單位面積風(fēng)管單位時(shí)間內(nèi)的允許漏風(fēng)量[m3/(h·m2)];
Where QL, QM, QH -- allowable air leakage of system air duct in unit time per unit area of air duct under corresponding working pressure [m3 / (H · m2)];
P——指風(fēng)管系統(tǒng)的工作壓力(Pa)。
P -- working pressure of air duct system (PA).
?、?低壓、中壓圓形金屬風(fēng)管、復(fù)合材料風(fēng)管以及采用非法蘭形式的非金屬風(fēng)管的允許漏風(fēng)量,應(yīng)為矩形風(fēng)管規(guī)定值的50%;
③ The allowable air leakage of low and medium pressure circular metal air ducts, composite air ducts and non-metal air ducts in non flange form shall be 50% of the specified value of rectangular air ducts;
?、?磚、混凝土風(fēng)道的允許漏風(fēng)量不應(yīng)大于矩形低壓系統(tǒng)風(fēng)管規(guī)定值的1.5倍;
④ The allowable air leakage of brick and concrete air duct shall not be greater than 1.5 times of the specified value of rectangular low-pressure system air duct;
?、?排煙、除塵、低溫送風(fēng)系統(tǒng)按中壓系統(tǒng)風(fēng)管的規(guī)定,1~5級(jí)凈化空調(diào)系統(tǒng)按高壓系統(tǒng)風(fēng)管的規(guī)定。
?、?The smoke exhaust, dust removal and low temperature air supply system shall be in accordance with the provisions of the medium pressure system air duct, and the level 1-5 purification air conditioning system shall be in accordance with the provisions of the high pressure system air duct.