鐵皮風(fēng)管質(zhì)量控制要點(diǎn)
發(fā)布人:http://rdhw.com.cn 發(fā)布時(shí)間:2022-07-22 15:15:44
1、風(fēng)管內(nèi)嚴(yán)禁有雜物或其它管線穿越,并做好清潔和保護(hù)工作;
1. Sundries or other pipelines are strictly prohibited to cross the air duct, and cleaning and protection work shall be done well;
2、支吊架下沿和外緣與接觸網(wǎng)帶電體(含承力索,下饋線等)間距保持大于230mm,并應(yīng)嚴(yán)格按照限界要求實(shí)施;
2. The safety distance between the lower edge and outer edge of the support and hanger and the electrified body of the overhead contact system (including messenger wire, lower feeder, etc.) shall be greater than 230mm, and shall be implemented in strict accordance with the clearance requirements;
3、連接螺栓應(yīng)為鍍鋅螺栓,同時(shí)需要配備相應(yīng)的平墊、彈墊和螺母;
3. Connecting bolts shall be galvanized bolts, and corresponding flat washers, spring washers and nuts shall be equipped;
4、風(fēng)管法蘭墊片的工作溫度不小于70℃;對(duì)于排煙風(fēng)管法蘭墊片的工作溫度要求不小于250℃;
4. The working temperature of the air duct flange gasket shall not be less than 70 ℃; The working temperature of flange gasket of smoke exhaust air duct shall not be less than 250 ℃;
5、風(fēng)管安裝的水平度允許偏差每米不應(yīng)大于3mm,總偏差不應(yīng)大于20mm;垂直安裝垂直度的允許偏差為每米不超過(guò)2mm,總偏差不應(yīng)大于20mm;
5. The allowable deviation of the levelness of the air duct installation shall not be greater than 3mm per meter, and the total deviation shall not be greater than 20mm; The allowable deviation of perpendicularity of vertical installation shall not exceed 2mm per meter, and the total deviation shall not be greater than 20mm;
6、風(fēng)管在穿過(guò)墻體或樓板處不得設(shè)置接口,風(fēng)管沿墻體或樓板安裝時(shí),距離墻面、樓板的間距應(yīng)大于150mm;
6. No interface shall be set at the place where the air duct passes through the wall or floor. When the air duct is installed along the wall or floor, the distance from the wall and floor shall be greater than 150mm;
7、風(fēng)閥的電動(dòng)執(zhí)行機(jī)構(gòu)安裝可靠固定,嚴(yán)禁隨意放置在風(fēng)管上;
7. The electric actuator of the air valve shall be installed reliably and firmly, and it is strictly forbidden to place it on the air duct at will;
8、手動(dòng)密閉閥安裝,閥門上標(biāo)志的箭頭方向需要與受沖擊波方向一致;
8. For the installation of manual closed valve, the direction of arrow marked on the valve shall be consistent with the direction of shock wave;
9、現(xiàn)場(chǎng)風(fēng)管接口的配置,不得縮小其有效截面;
9. The configuration of on-site air duct interface shall not reduce its effective section;
10、、空調(diào)風(fēng)管支吊架應(yīng)設(shè)不燃絕熱墊防止產(chǎn)生冷橋,絕熱墊應(yīng)在支吊架制作時(shí)錨固在橫擔(dān)上;
10. The supports and hangers of air-conditioning ducts shall be equipped with incombustible insulation pads to prevent cold bridges. The insulation pads shall be anchored on the cross arms when the supports and hangers are manufactured;
11、對(duì)系統(tǒng)風(fēng)管的檢測(cè),宜采用分段檢測(cè)、匯總分析的方法。在嚴(yán)格安裝質(zhì)量管理的基礎(chǔ)上,系統(tǒng)風(fēng)管的檢測(cè)以總管和干管為主。當(dāng)采用漏光法檢測(cè)系統(tǒng)的嚴(yán)密性時(shí),低壓系統(tǒng)風(fēng)管以每10m接縫,漏光點(diǎn)不大于2處,且100m接縫平均不大于16處為合格;中壓系統(tǒng)風(fēng)管每10m接縫,漏光點(diǎn)不大于1處,且100m接縫平均不大于8處為合格。
11. The method of segmented detection and summary analysis should be adopted for the detection of system air duct. On the basis of strict installation quality management, the main pipe and main pipe are mainly inspected for the system air duct. When the light leakage method is used to detect the tightness of the system, the low-pressure system air duct is qualified with no more than 2 light leakage points per 10m joints, and no more than 16 light leakage points per 100m joints on average; If the light leakage point of the air duct of the medium pressure system is not more than 1 every 10m joint, and the average number of joints is not more than 8 every 100m, it is qualified.
以上就是為大家介紹的有關(guān)濟(jì)南風(fēng)管加工廠的詳細(xì)的介紹,希望對(duì)您有所幫助.如果您有什么疑問(wèn)的話,歡迎聯(lián)系我們.我們將以的態(tài)度,為您提供服務(wù)http://rdhw.com.cn
The above is a detailed introduction about Jinan air duct processing factory. I hope it can help you. If you have any questions, please contact us. We will provide services for you with a professional attitude http://rdhw.com.cn
上一篇:通風(fēng)管道的兩種通風(fēng)方式是什么?
下一篇:通風(fēng)管道的連接方式
相關(guān)